42-337-30305

Final Completion

ORTON (CADDO) UNIT

MONTAGUE County · District 9 · SMITH PIPE OF ABILENE · ORTON (CADDO)

RRC Lookup

Permits

1

Max Depth

6,420 ft

First Permit

1987-05-29

Latest Activity

1987-05-29

Lifespan

< 1 yr

Regulatory Status

Schedule

OFF SCHEDULE

Completion

1987-10-22

Shut-In

Plugged

1999-02-12

!

EWA / Production operator mismatch

Scheduling: SMITH PIPE OF ABILENE ≠ Production: MITCHELL ENERGY CORPORATION (reported 1998-07)

!

EWA / Permit operator mismatch

Scheduling: SMITH PIPE OF ABILENE ≠ Permit: MITCHELL ENERGY CORPORATION

Resolved via: schedulingSMITH PIPE OF ABILENE

Production Summary

Cum Oil

bbl

Cum Gas

mcf

First Production

1993-01

Last Production

1999-09

Operator History

originally filed by MITCHELL ENERGY CORPORATION — asset transferred

Lease Production

Production is reported at the lease level. View production data, decline curves, and history on the lease page.

Permit Applications (1)

#330749 A MITCHELL ENERGY CORPORATION
received 1987-05-26

Well Details

Well Number
3
Max Depth
6,420 ft
Drill Type
Vertical
County
MONTAGUE
District
9
Completed
1987-10-22

Operator

Location
ABILENE
P-5 Status
Y (filed 2024-07-03)
Cum Oil (all leases)
17,644 bbl
Cum Gas (all leases)
14,486 mcf

External Links

Live © 2026 Petrora