NORWAY · WELLBORES · NPDID 476

34/10-23

Exploration · Wildcat · P&A · Gas · Den norske stats oljeselskap a.s · Valemon · PL 050

9 documents: reports, logs, and plots →

34/10-23 is a wildcat exploration wellbore in the North Sea, drilled by Den norske stats oljeselskap a.s, entered May 6, 1985, to 4,764 m in the Statfjord Gp.

Discovery 34/10-23 Valemon · On the map →

4,764
m total depth · 4,764 m vertical
135
m water depth
May 6, 1985
entered · completed Oct 13, 1985
Statfjord Gp
at total depth · Late Triassic
218.3
m of core in 11 cores
162
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED OCT 13, 1987

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
DYVI DELTA · Semisub steel
Drilling days
161
Kelly bushing elevation
29 m
Maximum inclination
0°
Drilling permit
465-L
Licensing round
Awarded additionally to round 3
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
61.01843° N, 2.31710° E
Hydrocarbons in
Tarbert Fm · Middle Jurassic

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Well 34/10-23 was drilled on the Gullfaks Gamma structure, south-southeast of the Gullfaks Sør Field in the Northern North Sea. The objectives were to prove a significant hydrocarbon accumulation, with the Brent Group as the primary target and the Early Jurassic as secondary target. The first well on the structure, well 34/10-20, had the same targets as 34/10-23, but was terminated in the Early Cretaceous due to technical problems.

Operations and results

Wildcat well 34/10-23 was spudded with the semi-submersible installation Dyvi Delta on 6 May 1985 and drilled to TD at 4764 m into Sinemurian /possibly Rhaetian age sediments of the Statfjord Formation. The well took 28 days more than prognosed to drill. The main part of the extra time came in the 8 1/2" section, where among many other things, the BOP stack was pulled for inspection and repairs. A flow occurred at 4080 m just above top Brent Group, and approximately three days were used to bring the well under control. At 4409 m (4406.5 m TVD RKB) the deviation exceeded 5 deg. The last survey, at 4514 m (4510.8 m TVD RKB) m showed 9.1 deg deviation. If this deviation is extrapolated the vertical depth at TD is 4756.2, ca 8 m short of measured depth. The well was drilled with seawater and hi-vis pills down to 1252 m, with gypsum/lignosulphonate mud from 1252 to 3118 m, and with gypsum/lignosulphonate/lignite mud from 3118 m to 4525 m. At 4509 m the pipe stuck, and imco-spot/pipelax pills with 3% diesel were placed to free it. The final section from 4525 m to TD was drilled with a gel/lignosulphonate/lignite/Anco Resin mud system.

The pore pressure increased through the entire Cretaceous section and reached a maximum of 1.96 g/cc at the top of the Brent Group. Gas bearin

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.

Developers: this page as JSON is GET /v1/data/norway/wells/476, documented in the API reference.