PERMITS · 617930-99 · DISTRICT 6

Drill: Viper 2 #8

Expired

EL Paso Production Company  ·  Rusk County  · Vertical  · Final completion

Apr 20, 2006
issued
11,200
permitted depth, ft
42-401-33917
API number
1
version on file

FIRST SEEN BY PETRORA APR 20, 2006 · WHY THIS DIFFERS FROM THE ISSUE DATE

Lifecycle

  1. Apr 20, 2006Received · Application received by the RRC
  2. Apr 20, 2006Issued · Permit approved
  3. Apr 27, 2006Spud · Drilling began
  4. Apr 28, 2006Surface casing · Surface string set
  5. May 16, 2006Well status · Final completion
  6. Apr 20, 2008Expired · Not drilled within the permit term

A drilling permit is valid for two years from issuance unless extended. How permits work →

Surface location

Acres
625.53
Nearest town
4.2 mi SE of Henderson
Nearest lease line
467 ft

No coordinates yet. The RRC's GIS record usually lands within days of issuance; permits from the historical master file never carry one.

Application records

Status entries the RRC filed against this permit number.

Status no.ReceivedStatusOperatorLease / well
617930-99Apr 20, 2006AEL Paso Production CompanyViper 2 #8