6407/9-7 is a wildcat exploration wellbore in the Norwegian Sea, drilled by A/S Norske Shell, entered Apr 26, 1988, to 2,561 m in the Red Beds (informal).
- 2,561
- m total depth · 2,561 m vertical
- 241
- m water depth
- Apr 26, 1988
- entered · completed May 25, 1988
- Red Beds (informal)
- at total depth · Late Triassic
- —
- m of core
- 74
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED MAY 25, 1990
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- TREASURE SCOUT · Semisub steel
- Drilling days
- 30
- Kelly bushing elevation
- 23 m
- Maximum inclination
- 2°
- Drilling permit
- 577-L
- Licensing round
- 8
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 64.49668° N, 7.86247° E
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Well 6407/9-7 was located on the crest of the "Husky" structure approximately 11 km NNE of Draugen well 6407/9-2.
The main objectives of the well were: to evaluate the hydrocarbon potential of the Middle Jurassic sandstones of the "Husky" prospect; to evaluate the Early Jurassic sands; to fulfil the work obligation of the licence by drilling a second exploration well into the Triassic.
Operations and results
Wildcat well 6407/9-7 was spudded with Wilh. Wilhelmsen semi-submersible installation Treasure Scout on 26 April 1988 and drilled to TD at 2561 m in the Triassic Red Beds. The well was drilled with Seawater and hi-vis pills down to 810 m and with KCl/Polymer mud from 810 m to TD. The drilling proceeded without problems. No shallow gas was encountered.
The target Middle and Early Jurassic reservoir sands were well developed, particularly in the Garn Formation. There were no signs of hydrocarbons, either within the Jurassic sequence or in the overlying section. The well was considered a conclusive dry test of the Husky structure.
No cores were cut and no fluid samples were taken. The well was permanently abandoned on 25 May 1988 as a dry well.
Testing
No drill stem test was performed
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/1057, documented in the API reference.