2/7-20 is a wildcat exploration wellbore in the North Sea, drilled by Phillips Petroleum Company Norway, entered Oct 15, 1987, to 4,509 m in the No Group Defined.

Discovery 2/7-20 Embla · On the map →

4,509
m total depth · 4,508 m vertical
70.8
m water depth
Oct 15, 1987
entered · completed Jun 25, 1988
No Group Defined
at total depth · Devonian
41.3
ft of core in 4 cores
167
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED JUN 25, 1990

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
DYVI STENA · Semisub steel
Drilling days
255
Kelly bushing elevation
25 m
Maximum inclination
5.19999981°
Drilling permit
566-L
Licensing round
1-A
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
56.33325° N, 3.24829° E
Hydrocarbons in
No Group Defined · Devonian

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Well 2/7-20 was drilled on the "South Eldfisk structure", later called Embla. The 2/7-9 well, drilled in 1973, tested oil at uneconomic rates from a thick pre-Late ?Jurassic sand sequence on this structure. Well 2/7-9 established a 111 m pay section with average porosity of 13% and 55% oil saturation. A clear OWC was found at 4387 m MSL. Following a 1986 re-evaluation of the test it was concluded that the poor test results might have been due to mechanical problems. Subsequently the 2/7-20 well was spudded to test the previously encountered sandstones. The objectives of the well were to test "economic" flow rates from sands on the South Eldfisk structure below the Late Jurassic shales of the Mandal Formation. At the time of drilling the cost of a subsea completion had been estimated to be US$ 12 million which meant that flow rates in excess of 286 m3 oil/day were considered economic. Well 2/7-20 was placed on a separate and higher fault block in the structure than the one drilled by 2/7-9.

Operations and results

Wildcat well 2/7-20 was spudded with the semi-submersible installation Dyvi Stena on 15 October 1987. The well was re-spudded three times because of collapsed hole problems. After drilling riserless to 608 m the lower part of the hole collapsed after encountering a gas sand that resulted in the loss of drill pipe. The well was sidetracked at 234 m, and 13 3/8" casing was set above the Eocene at 2439 m. A drilling break was encountered at 4084 m. After drilling a further 2 m, 100% sands with good shows were circulated up. High pressures together with the long section of open hole necessitated plugging back and sidetracking immediately below the 13 3/8" casing shoe. No logs were run at TD in this hole before plugging back. Drilling the sid

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.