NORWAY · WELLBORES · NPDID 112
16/11-1 S
Exploration · Wildcat · P&A · Dry · Phillips Petroleum Company Norway · PL 016
16/11-1 S is a wildcat exploration wellbore in the North Sea, drilled by Phillips Petroleum Company Norway, entered Jul 14, 1967, to 3,050 m in the Zechstein Gp.
- 3,050
- m total depth · 3,020 m vertical
- 67
- m water depth
- Jul 14, 1967
- entered · completed Oct 31, 1967
- Zechstein Gp
- at total depth · Late Permian
- —
- m of core
- 100
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED OCT 31, 1969
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- OCEAN VIKING · Semisub steel
- Drilling days
- 110
- Kelly bushing elevation
- 27 m
- Maximum inclination
- 16°
- Drilling permit
- 4-L
- Licensing round
- 1-A
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- No
- Position · ED50
- 58.06778° N, 2.56889° E
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
Well 16/11-1 S is located in the Danish Norwegian Basin. The objective of the well was to test the hydrocarbon potential of the Tertiary, Mesozoic and Permian sediments. Specifically, Tertiary sandstones, Cretaceous sandstones and limestones, Jurassic and Triassic sandstones, Permian carbonates and Permian Rotligendes sandstone were considered to be prospective.
Operations and results
Wildcat well 16/11-1 S was spudded with the semi-submersible installation Ocean Viking on 17 July 1967 and drilled to TD at 3050 m (ca 3020 m TVD RKB) in the Late Permian Zechstein Group. The well is classified as deviated, but was not meant to be. During reaming operation at about 1463 m the hole was accidentally sidetracked. This was not discovered until 13 3/8" casing was set and the cement plug drilled through. Hole deviation was then determined to be 16 deg at the casing shoe. In order to prevent a dogleg the deviation was gradually decreased to 12.5 deg at about 2322 m and stabilized at an average of 12 deg to TD. The dip meter log indicates that the hole drifted in a N 45 deg E direction. While drilling at 2952 m the drill string stuck and a fish was left in the hole. A cement plug was set and the fish was bypassed by sidetracking with jet action from the bit. Upon reaching 2952 m, the pipe stuck a second time, which resulted in leaving a new fish. A second cement plug was set and the hole sidetracked using a Neyrpic turbine drill. The pipe stuck a third time at 2954 m and another fish was left. The hole was again sidetracked and mud weight increased to about 16 ppg. Drilling then continued to TD, before 9 5/8" casing was set. Circulation was lost immediately after drilling through the 9 5/8" casing shoe at 2957 m. Five Diaseal "M" squeezes and five DOC squeezes were performed in an attempt to regain circulation with a 16.0 ppg mud, but all attempts were unsuccessful. A Drispac/Flosal/Desco mud system was used to a depth of 2326 m. At this de
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/112, documented in the API reference.