NORWAY · WELLBORES · NPDID 1224
2/8-11
Exploration · Appraisal · P&A · Oil · Amoco Norway Oil Company · Valhall · PL 006
2/8-11 is an appraisal exploration wellbore in the North Sea, drilled by Amoco Norway Oil Company, entered Aug 10, 1976, to 2,655 m in the Rødby Fm.
Discovery 2/8-6 Valhall · On the map →
- 2,655
- m total depth
- 70
- m water depth
- Aug 10, 1976
- entered · completed Oct 11, 1976
- Rødby Fm
- at total depth · Early Cretaceous
- 12.2
- ft of core in 2 cores
- 74
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED OCT 11, 1978
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- ROSS RIG (1) · Semisub steel
- Drilling days
- 63
- Kelly bushing elevation
- 25 m
- Maximum inclination
- 0°
- Drilling permit
- 164-L
- Licensing round
- 1-A
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 56.28231° N, 3.37100° E
- Hydrocarbons in
- Tor Fm · Late Cretaceous
- Hydrocarbons in
- Hod Fm · Late Cretaceous
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Well 2/8-11 was drilled as a field delineation well intended to help establish the commerciality of the southern North Sea Valhall Field, which was discovered by well 2/8-6 and confirmed by wells 2/8-8, 2/8-9 and 2/8-10. The primary objective was to test the Late Cretaceous chalk reservoirs and to estimate the presence of hydrocarbons.
Operations and results
Appraisal well 2/8-11was spudded with the semi-submersible installation Ross Rig on 10 August 1976 and drilled to TD at 2655 m in the Early Cretaceous Rødby Formation. The well was drilled in a total of 33 days without any major drilling problems. However, 13 days were spend on logging in the 12 1/4-inch hole and setting and cementing two completion strings comprising of a 7-inch liner cemented inside the 9 5/8-inch casing. The well was drilled with seawater/bentonite/caustic soda down to 381 m, with Drispac/Dextrid/lignosulphonate mud from 381 m to 1294 m, and with Drispac/Dextrid/lignosulphonate/Soltex mud from 1294 m to TD.
The well penetrated a normal Quarternary-Tertiary sequence with the top Paleocene Ash Marker at 2437 m, 51m lower than predicted. The Late Cretaceous Maastrichtian chalk (Tor Formation) was encountered at 2468 m with a total thickness of 15 m and with an oil column of the same magnitude. The porosity was 40-50% and the water saturation close to zero. The two Coniacian-Turonian reservoirs, (upper and lower Hod Formation) had porosities of 30-40% and water saturations averaging 50% with 18.5 m pay in the upper reservoir and 33.5 m pay in the lower reservoir. The Turonian shale was penetrated at 2612 m and the top of the Early Cretaceous was reached at 2624 m giving a total chalk thickness of 144 m.
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/1224, documented in the API reference.