9/8-1 is a wildcat exploration wellbore in the North Sea, drilled by Esso Exploration and Production Norway A/S, entered May 23, 1968, to 2,176 m in the Zechstein Gp.
- 2,176
- m total depth
- 68
- m water depth
- May 23, 1968
- entered · completed Jun 29, 1968
- Zechstein Gp
- at total depth · Late Permian
- 23.9
- m of core in 2 cores
- 75
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED JUN 29, 1970
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- ENDEAVOUR · Jack-up 3 legs
- Drilling days
- 38
- Kelly bushing elevation
- 30 m
- Maximum inclination
- 4°
- Drilling permit
- 5-L
- Licensing round
- 1-A
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 57.34277° N, 4.33694° E
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
The 9/8-1 well is located in the central western part of the Norwegian-Danish Basin in the North Sea. The objective was to test the hydrocarbon potential of the sedimentary section present on the crest of a closed seismic structure interpreted to be a salt pillow. Prospective reservoir sands were anticipated towards the base of the Tertiary, in the Early Cretaceous and in the Early Triassic.
Operations and results
Wildcat well 9/8-1 was spudded with the jack-up installation Endeavour on 23 May 1968 and drilled to TD at 2176 m in the Late Permian Zechstein Group. It was the first well drilled in Norwegian waters with a jack-up platform. After the 36" conductor was set at 137 m, the hole was drilled with a 17 1/2" bit to 411 m. While reaming the hole to 26", cavings and fill of shell fragments and gravel caused problems from about 300 m, necessitating the 20" casing to be set high at 360 m. The only additional drilling problem of note was a twist off while drilling at 1546 m. The fish was recovered in a few hours without difficulty. From here, operations were successfully carried out to TD. Initial drilling from the sea floor to 1350 feet was with seawater and gel without casing. Returns were to the sea floor. Below 1350 to TD at 7138 feet, a Spersene, XP-20, Salinex mud with up to 10 % diesel oil was used.
The interpreted salt pillow structure was found to be a piercement which breached the Triassic with the result that the
Triassic Bunter sand section was not present in this well. Top Permian Zechstein evaporites at 2109 m were immediately overlain by the Middle Jurassic Dogger formation. The Dogger contained some porous sandstones (Sandnes Formation) but these had only weak shows in the uppermost few feet and the logs indicated high water saturation. Both the Lower Cretaceous and the entire Tertiary section consisted mainly of clays. No sands were developed at the base of either the Lower Cre
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.