NORWAY · WELLBORES · NPDID 1467

3/7-4

Exploration · Wildcat · P&A · Gas/condensate · A/S Norske Shell · Trym · PL 147

5 documents: reports, logs, and plots →

3/7-4 is a wildcat exploration wellbore in the North Sea, drilled by A/S Norske Shell, entered Sep 20, 1989, to 3,723 m in the Zechstein Gp.

Discovery 3/7-4 Trym · On the map →

3,723
m total depth · 3,721 m vertical
66
m water depth
Sep 20, 1989
entered · completed Jan 23, 1990
Zechstein Gp
at total depth · Late Permian
144.7
m of core in 8 cores
136
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED JAN 23, 1992

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
HUNTER · Semisub steel
Drilling days
126
Kelly bushing elevation
25 m
Maximum inclination
7.30000019°
Drilling permit
619-L
Licensing round
12
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
56.40433° N, 4.23951° E
Hydrocarbons in
Sandnes Fm · Middle Jurassic
Hydrocarbons in
Bryne Fm · Middle Jurassic

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Well 3/7-4 was designed to drill a prospect on the Lulita culmination. The Lulita prospect extends in to Danish waters, and forms part of an elongated, N-S trending, salt induced feature on the western margin of the Søgne Basin. The present structural features were developed during mid Cretaceous time, and closure at Late Cretaceous and Tertiary levels essentially reflects compaction and drape over the Jurassic high. The Jurassic Lulita closure is separated from the area tested by the 3/7-3 well by a faulted saddle, which also is well expressed at Tertiary and Cretaceous levels, providing a vertical closure of some 75 metres. The well had as primary objective to test the hydrocarbon potential of Middle Jurassic sandstones within a structural/stratigraphic trap, and as secondary objective to testing the potential in possible Late Jurassic and Early Cretaceous sandstones, within a structural trap. Additional objectives included testing of Late Cretaceous Chalk, found hydrocarbon bearing in the nearby Harald field, Paleocene/Eocene turbiditic sandstones, and the reservoir quality of the Triassic sequence. The well should drill some 150 m into rocks of Triassic age. Shallow gas could be encountered at 317 to 388 m, at 485, and at 515 m according to seismic anomalies.

Operations and results

Wildcat well 3/7-4 was spudded with the semi-submersible installation Hunter on 20 September 1989 and drilled to TD at 3723 m in the Permian Zechstein Group. At 3472.9 m the string was backed off, and a cement kick off plug was set. The hole was sidetracked from 3405 m. The well was drilled with seawater and hi-vis spud mud down to 622 m, with KCl polymer from 622 m to 3473 m, and with seawater/polymer from 3473 m to TD. No shallow gas was encountered.

A 160 m hydrocarbon column from top Ula Formation and down to 3572 m in the Bryne Formation was found from well-logs, core shows, and RFT pressure gradients. Strong shows were recorded throughou

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.

Developers: this page as JSON is GET /v1/data/norway/wells/1467, documented in the API reference.