NORWAY · WELLBORES · NPDID 1563

7/11-10 S

Exploration · Appraisal · Suspended · Oil · Norsk Hydro Produksjon AS · Mime · PL 070

4 documents: reports, logs, and plots →

7/11-10 S is an appraisal exploration wellbore in the North Sea, drilled by Norsk Hydro Produksjon AS, entered Jul 5, 1990, to 4,566 m in the Smith Bank Fm.

Discovery 7/11-5 Mime · On the map →

4,566
m total depth · 4,241 m vertical
78.5
m water depth
Jul 5, 1990
entered · completed Sep 10, 1990
Smith Bank Fm
at total depth · Triassic
45.5
m of core in 3 cores
169
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED SEP 10, 1992

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
TRANSOCEAN 8 · Semisub steel
Drilling days
68
Kelly bushing elevation
23.5 m
Maximum inclination
50°
Drilling permit
641-L
Licensing round
6
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
57.12014° N, 2.48627° E
Hydrocarbons in
Ula Fm · Late Jurassic

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Well 7/11-10 S was designed to drill the 7/11-A structure on the Mime Field, on the eastern margin of the Central Graben. The structure is salt induced and consists of a northern, western, eastern and a southern compartment. Oil is proven in the northern compartment by the 7/11-5 well in the Late Jurassic Ula formation sandstone. The reservoir sandstone was deposited in a shallow marine environment mainly by storm episodes into an approximately 100 km long and 20 km wide "fairway". Shales of the Late Jurassic Farsund- and Mandal formations make up the cap-rock. The well was to be vertical down to 2002 m MSL and then kicked off towards the target with an angle of 33.28 degrees. The primary objective was a long term test production from the oil-bearing Ula formation of Area 1 in the northern compartment. Secondary objective was to improve the geological control, and coring was supposed to give good information about the silica cementation above and below the OWC. Shallow gas was indicated in the interval from 318 m - to 425 m MSL.

Operations and results

Appraisal well 7/11-10 S was spudded with the semi-submersible installation Transocean 8 on 5 July 1990 and drilled to TD at 4566 m in the Triassic Smith Bank Formation. No shallow gas of importance, only background gas, was encountered while drilling. Gumbo problems were encountered in the upper part of the 17 1/2" hole, but hole conditions improved after increasing the mud weight. The well was kicked off at 2010 m in 40° direction, and the angle built to 35° at 2610 m. While pulling out, the bit came out with three cones lost. The string got stuck at 3740 m. Fishing operation was unsuccessful, and a cement plug was set above the fish. The hole was kicked off from the cement plug at 3550 m and sidetracked. No severe problems were experienced in the last part of the hole except from low penetration rate at times and some tight spots on the bit trips. The top hole was dr

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.

Developers: this page as JSON is GET /v1/data/norway/wells/1563, documented in the API reference.