NORWAY · WELLBORES · NPDID 1672
25/11-14 S
Exploration · Appraisal · Suspended · Oil · Esso Exploration and Production Norway A/S · Balder · PL 001
25/11-14 S is an appraisal exploration wellbore in the North Sea, drilled by Esso Exploration and Production Norway A/S, entered Sep 13, 1990, to 1,908 m in the Heimdal Fm.
Discovery 25/11-1 Balder · On the map →
- 1,908
- m total depth · 1,749 m vertical
- 127
- m water depth
- Sep 13, 1990
- entered · completed Oct 13, 1990
- Heimdal Fm
- at total depth · Paleocene
- 21.6
- m of core in 5 cores
- 85
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED OCT 13, 1992
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- BYFORD DOLPHIN · Semisub steel
- Drilling days
- 31
- Kelly bushing elevation
- 25 m
- Maximum inclination
- 44.40000153°
- Drilling permit
- 648-L
- Licensing round
- 1-A
- Plugged and abandoned
- Oct 13, 1990
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 59.18814° N, 2.36990° E
- Hydrocarbons in
- Heimdal Fm · Paleocene
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Well 25/11-14 S was drilled centrally on the Balder Field on the Utsira High in the North Sea. This field was discovered in 1967 by the 25/11-1 well, and was the first well on the Norwegian shelf that proved oil. Well 25/11-14 S was planned to be completed for a long term test by the FPV Petrojarl 1. The well was planned deviated in order to avoid possible shallow gas at 235 m, 254 m, and 515 m. The main objective of this well was to test two Paleocene Heimdal Formation sands; the IB4 sand at 1863 m and the IB3 sand at 1897 m. The Heimdal Formation had previously proved oil-bearing in the three neighbouring wells 25/11-6, -7, and -8. Eocene sands constituted a secondary objective for testing. Based on data from surrounding wells, no abnormal pressure was expected. The surface location and well trajectory for this well, was designed so that a later plug-back and sidetrack to a horizontal completion could be accomplished.
Operations and results
Appraisal well 25/11-14 S was spudded with the semi-submersible installation Byford Dolphin on 13 September 1990. During setting of the 30" casing a fatal accident occurred as one of the roughnecks was hit by the rig tongs and perished on the drilling floor. A 9 7/8" pilot was drilled with MWD from 189 m to check possible shallow gas. Sands were detected, but they contained salt water only. The planned deviation was initiated at 950 m. While POOH for coring the Heimdal Formation sand, the pipe became stuck (packed off by sloughing shales) and the well bore abandoned at a TD of 1908 m (1749 m TVD), 5 m into the target Heimdal Formation. The well was drilled with seawater down to 452 m and with KCl/polymer/gel mud from 452 m to TD.
The secondary target Eocene sands were not pre
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.