7119/12-3

Exploration · Wildcat · P&A · Gas/condensate · Den norske stats oljeselskap a.s · PL 060

7 documents: reports, logs, and plots →

7119/12-3 is a wildcat exploration wellbore in the Barents Sea, drilled by Den norske stats oljeselskap a.s, entered May 20, 1983, to 3,314 m in the Nordmela Fm.

Discovery 7119/12-3 · On the map →

3,314
m total depth · 3,308 m vertical
211
m water depth
May 20, 1983
entered · completed Sep 12, 1983
Nordmela Fm
at total depth · Early Jurassic
26.4
m of core in 3 cores
136
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED MAR 1, 2026 · RELEASED SEP 12, 1985

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
DYVI DELTA · Semisub steel
Drilling days
116
Kelly bushing elevation
29 m
Maximum inclination
7°
Drilling permit
376-L
Licensing round
5
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
71.23894° N, 19.74387° E
Hydrocarbons in
Stø Fm · Jurassic

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

The primary objective of wildcat 7119/12-3 was to test possible hydrocarbon accumulations in sandstones of Middle to Lower Jurassic age. Gas and condensate were discovered in the sandstone sequences. Planned TD was 3765 m.

Operations and results

Exploration well 7119/12-3 was spudded with the semi-submersible installation Dyvi Delta on 20 may 1982 and drilled to TD at 3314 m in the Early Jurassic Nordmela Formation. A total of 121 days was spent on this well including testing and a 9.5 days seamen's strike. The time estimate was 106 days. No major problems occurred due to drilling. The well was drilled using spud mud down to 303 m, with gel/seawater from 303 m to 716 m, with gypsum/polymer from 716 m to 1618 m, and with gel/lignosulphonate from 1618 m to TD.

Hydrocarbon accumulations were discovered in sandstone sequences between 3144 - 3285 m in the Stø Formation. From log evaluation the interval contained 118 m net sand. The gas/water contact at 3285 m is based on the log evaluation. Due to very tight and hard formation only two RFT pressure points were obtained out of 16 attempts (seal failures). Organic geochemical analyses found only poor source rock potential in the well. Shales in the Late Jurassic Hekkingen Formation from 3026 m to 3107 m had high TOC levels in the range 3% to 9%. However, with Hydrogen Indexes only in the range 30 - 40 mg HC/g TOC in non-caved, high-TOC samples, these shales are gas prone, and can not produce any significant quantities of liquid hydrocarbons. The well is immature down to ca 2300 m and reaches oil window maturity at ca 3000 m. Three cores were cut in the sandstones of the Middle to Early Jurassic Stø Formation. The two first were cut in the interval 3145 m to 3154.85 m with 100 % recovery. The third was cut from 3250 m to 3267 m with 97 % recovery. One RFT segregated sample was taken at 3187 m. The 2 3/4 -gallon chamber was bled off on the rig. It had an opening pressure of 38.9 ba

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.

Developers: this page as JSON is GET /v1/data/norway/wells/17, documented in the API reference.