NORWAY · WELLBORES · NPDID 1816
30/10-6
Exploration · Wildcat · P&A · Gas · Elf Petroleum Norge AS · PL 142
30/10-6 is a wildcat exploration wellbore in the North Sea, drilled by Elf Petroleum Norge AS, entered Jan 13, 1992, to 5,248 m in the Ness Fm.
Discovery 30/10-6 · On the map →
- 5,248
- m total depth · 5,246 m vertical
- 91
- m water depth
- Jan 13, 1992
- entered · completed Nov 9, 1992
- Ness Fm
- at total depth · Middle Jurassic
- 83.2
- m of core in 6 cores
- 180
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED MAR 1, 2026 · RELEASED NOV 9, 1994
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- WEST ALPHA · Semisub steel
- Drilling days
- 302
- Kelly bushing elevation
- 18 m
- Maximum inclination
- 3°
- Drilling permit
- 712-L
- Licensing round
- 11-B
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 60.15379° N, 2.21038° E
- Hydrocarbons in
- Tarbert Fm · Middle Jurassic
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
The exploration well 30/10-6 is situated in the central part of block 30/10, approximately 10km north of the Odin Field. The structure is part of the Jurassic fault block system forming at NE-SW trending complex from the Frigg area to the Southeastern part of block 30/7. The objective of well 30/10-6 was to explore the hydrocarbon potential of the Middle Jurassic Brent Group. Top Brent was prognosed at 5120 m.
Operations and results
The well 30/10-6 was spudded 13 January 1992 by the semi submersible rig West Alpha and was completed the 11 November 1992 at a TD of 5250 in the Middle Jurassic Ness Formation of the Brent Group. Due to too much inclination of the well, it had to be spudded three times. The verticality was critical due to possible severe casing wear in a deep well. After the third spud the drill string got stuck at 620 m in the 26" section. Fishing was unsuccessful and as verticality was important the well was respudded again. If plugging is not considered, the total duration of the well was 206 days for the drilling part. This includes 22 days on the three first spuds and 184 days on the final well. Compared to the planned 114 days (114 = 125 -11 for P&A) this yields a total delay of 92 days. The well was drilled with Bentonite mud down to 1420 m, with gypsum mud from 1420 m to 4368 m, and with polymer mud from 4368 m to TD.
A seismic reflector depth converted to 4850 m (+ /- 200m), was interpreted as a "Callovian Unconformity", possibly with sand stringers. This seismic reflector proved to be top Tarbert Formation at 4666 m. The Tarbert Formation could be divided into two an Upper Sand (4666 m to 4815 m) and a Lower Sand (4884.5 m to 5207 m) separated by a 70 m thick shale unit. The top part of the Upper Sand contained gas. It was not possible to establish a free water level or a gas/water contact. The reservoir characteristics were poor and commercial production was not found to be possibl
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/1816, documented in the API reference.