NORWAY · WELLBORES · NPDID 2044
2/5-10
Exploration · Wildcat · P&A · Oil shows · Norsk Agip AS · PL 067
2/5-10 is a wildcat exploration wellbore in the North Sea, drilled by Norsk Agip AS, entered May 23, 1993, to 4,701 m in the Skagerrak Fm.
- 4,701
- m total depth · 4,700 m vertical
- 65
- m water depth
- May 23, 1993
- entered · completed Aug 26, 1993
- Skagerrak Fm
- at total depth · Triassic
- 15
- m of core in 2 cores
- 165
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED MAR 1, 2026 · RELEASED AUG 26, 1995
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- POLAR PIONEER · Semisub steel
- Drilling days
- 96
- Kelly bushing elevation
- 23 m
- Maximum inclination
- 2.79999995°
- Drilling permit
- 761-L
- Licensing round
- 6
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 56.68935° N, 3.49092° E
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Exploration well 2/5-10 is located in the Central Graben on the Steinbit Terrace. The well was drilled with Late Jurassic sandstone of Oxfordian age, in a combination trap with structural and dip closing elements, as the primary target. Secondary targets were the Middle Jurassic Bryne Formation in the same combination trapping configuration, while the Late Cretaceous Chalk and the Lower Cretaceous Cromer Knoll Group were stratigraphic trap targets. After reaching TD evaluation of the cores and electric logs concluded that a fault had been intercepted within the main Jurassic target, justifying a sidetrack in search of a better pay zone. Well 2/5-10 was therefore plugged back in and well 2/5-10 A sidetracked.
Operations and results
Well 2/5-10 was spudded with the semi-submersible installation "Polar Pioneer" on 23 May 1993 and drilled to TD at 4701 m in rocks of the Triassic Smith Bank Formation. The well was drilled with sea water and hi-vis sweeps down to 865 m, with KCl/Polymer mud from 865 m to 4235 m, and with HPHT/Polymer mud from 4235 m to TD. Shallow gas was encountered after drilling the 8 1/2" pilot hole, prior to opening up the hole to 26" and running 20" casing. In order to ensure a good 20" casing cement job without compromising rig safety it was decided to plug back the gas bearing zone and set 20" casing at 509m, 291m shallower than originally planned 800m. To avoid gas migration the cement slurries for the 20" and 13 3/8" were redesigned with gas tight cement (microblock added).
Top reservoir was encountered at 4582 m, 174 m deeper than prognosis due to complex geology and higher than expected shale interval velocities in the Late Jurassic. The main part of the Late Jurassic sandstone target was removed by faulting, and Triassic strata were encountered 5 m below top reservoir through a fault plane. The Late Jurassic sandstone was highly affected by the faulting,
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/2044, documented in the API reference.