6406/2-1 is a wildcat exploration wellbore in the Norwegian Sea, drilled by Saga Petroleum ASA, entered Oct 30, 1994, to 5,292 m in the Åre Fm.
Discovery 6406/2-1 Lavrans · On the map →
- 5,292
- m total depth · 5,283 m vertical
- 278
- m water depth
- Oct 30, 1994
- entered · completed Apr 9, 1995
- Åre Fm
- at total depth · Early Jurassic
- 616.8
- m of core in 28 cores
- 172
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED APR 9, 1997
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- ROSS RIG (2) · Semisub steel
- Drilling days
- 162
- Kelly bushing elevation
- 24 m
- Maximum inclination
- 15.30000019°
- Drilling permit
- 798-L
- Licensing round
- 14
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 64.87089° N, 6.60593° E
- Hydrocarbons in
- Fangst Gp · Middle Jurassic
- Hydrocarbons in
- Båt Gp · Early Jurassic
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Exploration well 6406/2-1 was drilled on the B-prospect east in the block 6406/2, south of the Smørbukk Field and west of the Trestakk Field on Haltenbanken. The main purpose was to test the B-prospect sandstones of Middle to Early Jurassic age and the presence of hydrocarbons. Further, the reservoir quality at great depth (prognosed TD 5200 m) was to be tested. The main reservoir zones were prognosed to be the Ile and Tilje Formations, both prognosed to consist of mica-bearing sandstones with thin shale layers. The Garn and Tofte Formations, expected to be purer quartz-sandstones and more susceptible to diagenetic quartz cementation, were considered as additional potential.
Possible sandstones were also prognosed at three different levels within the Cromer Knoll Group (in the Lysing and Lange Formations, of Turonian and Cenomanian age), and the well 6406/2-1 was aimed to test these levels within structural closure.
Operations and results
Well 6406/2-1 was spudded on 31 October 1994 with the semi-submersible "Ross Rig" . Due to environmental restrictions in the area, the drilling operations was stopped on 1 April 1995, and the well was temporarily plugged and abandoned on 9 April 1995 at a preliminary TD of 5295 m. Total non-productive time (NPT) for the well was 49,3 days. The reasons for lost time were mainly:
- Core barrel stuck when attempting to pull out of hole with core no. 7
- Leakages on hose between yellow pod and shuttle valve for MPR
- Stuck with 2 radioactive logging tools
- Unsuccessful attempts to log with RCI / FMT tools
The well 6406/2-1 R was reentered 21 August 1995 and reached TD 20 September at 5892 m (5790 mTVD). The production testing of seven Jurassic reservoir levels was started 28 September 1995, and was completed 1 January 1996. The planned TD for the reentry was changed during drilling to 5800 m or 100 m below the Intra Åre Coal Sequence, in order to investigate the reservoir potential of the un
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/2444, documented in the API reference.