NORWAY · WELLBORES · NPDID 3314

34/11-4

Exploration · Appraisal · P&A · Gas/condensate · Den norske stats oljeselskap a.s · Valemon · PL 193

11 documents: reports, logs, and plots →

34/11-4 is an appraisal exploration wellbore in the North Sea, drilled by Den norske stats oljeselskap a.s, entered Dec 9, 1998, to 4,438 m in the Cook Fm.

Discovery 34/10-23 Valemon · On the map →

4,438
m total depth · 4,437 m vertical
133
m water depth
Dec 9, 1998
entered · completed Apr 14, 1999
Cook Fm
at total depth · Early Jurassic
50.2
m of core in 2 cores
159
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED APR 14, 2001

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
TRANSOCEAN ARCTIC · Semisub steel
Drilling days
127
Kelly bushing elevation
24 m
Maximum inclination
2.29999995°
Drilling permit
947-L
Licensing round
14
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
61.05728° N, 2.37958° E
Hydrocarbons in
Ness Fm · Middle Jurassic
Hydrocarbons in
Tarbert Fm · Middle Jurassic

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Block 34/11 is geographically located in the eastern part of the Tampen Spur, adjacent to the western controlling fault of the North Viking Graben. Structurally 34/11 is situated over a large, complex fault terrace down thrown to the south east of the Tampen Spur. The Mats Segment, which was tested with this well, is situated in the southwest part of block 34/11, and represents an easterly extension of the Gullfaks Gamma discovery in block 34/10. The Brent Group reservoir within the Gullfaks Gamma structure is within a high pressure, high temperature geological environment being at over 4000 m depth, with temperatures of 150 deg C. The main objective of the appraisal well 34/11-4 was to appraise additional hydrocarbon reserves in the Brent Group. Secondary objectives were to improve the geological / geophysical engineering parameter database, provide a key velocity calibration point to aid depth conversion, and to give a better understanding of the hydrocarbon characteristics, fluid contacts and distribution within the southern part of the 34/11 block.

Operations and results

Appraisal well 34/11-4 was spudded on 9 December 1998 with the semi-submersible installation "Transocean Arctic" and drilled to 3938 m. An unsuccessful cement job on the 9 7/8" casing resulted in backing off several joints of the casing. The casing was cut and retrieved from below the 13 3/8" shoe. The well was then sidetracked (34/11-4 T2) from 3580 m on 7 February 1999 and the 9 7/8" casing was successfully run and cemented at 3939 m. The T2 track was drilled to TD at 4438 m in the Early Jurassic Cook Formation, then logged and sampled (water and hydrocarbon samples). The initial well track was drilled with water based "Quadrill" mud containing 2 & 5 % polyols, a glycol-additive. The T2 track was drilled oil-based. Finally, an 8 1/2" sidetrack, 34/11-4 T3, was kicked-off at 4098 m on 31 March 1999 and drilled to 4210 m. T

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.

Developers: this page as JSON is GET /v1/data/norway/wells/3314, documented in the API reference.