NORWAY · WELLBORES · NPDID 349

25/1-3

Exploration · Appraisal · P&A · Oil/gas · Elf Petroleum Norge AS · Frigg · PL 024

6 documents: reports, logs, and plots →

25/1-3 is an appraisal exploration wellbore in the North Sea, drilled by Elf Petroleum Norge AS, entered Nov 14, 1971, to 2,872 m in the Shetland Gp.

Discovery 25/1-1 Frigg · On the map →

2,872
m total depth
105
m water depth
Nov 14, 1971
entered · completed Jan 27, 1972
Shetland Gp
at total depth · Late Cretaceous
44.6
m of core in 4 cores
67
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED JAN 27, 1974

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
PENTAGONE 81 · Semisub steel
Drilling days
75
Kelly bushing elevation
24 m
Maximum inclination
0°
Drilling permit
65-L
Licensing round
2-A
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
59.90139° N, 2.16806° E
Hydrocarbons in
Frigg Fm · Eocene

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Well 25/1-3 was drilled to appraise the eastward extension of the 25/1-1 Frigg Discovery on the Frigg Ridge in the North Sea. The primary objective was to test the Eocene sandstones that were gas bearing in well 25/1-1.

Operations and results

Appraisal well 25/1-3 was spudded with the semi-submersible installation Pentagone 81 on 14 November 1971 and drilled to TD at 2872 m in the Late Cretaceous Shetland Group. The well was drilled with seawater down to 405 m and with a seawater/LFC mud from 405 m to TD.

The target Eocene sandstones (Frigg Formation) was penetrated at 1952 m. The gross thickness was 217 m and the N/G was 0.82 with porosities ranging from 28 to 33%. It was gas bearing down to the GOC at 1973 m and oil bearing down to the OWC at 1982.5 m. Good oil shows on cores were recorded throughout the hydrocarbon-bearing reservoir. Weaker oil shows on cores were described ("fluo but salty taste") below the OWC.

Three cores were cut from 1951 to 2005 m in the Frigg reservoir. Total recovery for these three cores was 42.25 m (78.2% recovery). A fourth core was cut from 2563 to 2568 m with 50% recovery. FIT fluid samples were attempted at 2550.5 m and 2576.3 m but only mud and filtrate was recovered.

The well was permanently abandoned on 27 January 1972 as an oil and gas appraisal well

Testing

Six drill stem tests were conducted.

DST 1, 2 and 3 tested the interval 1985 to 1987 m. All three tests produced water.

<p

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.

Developers: this page as JSON is GET /v1/data/norway/wells/349, documented in the API reference.