NORWAY · WELLBORES · NPDID 4602
6403/10-1
Exploration · Wildcat · P&A · Dry · Norsk Hydro Produksjon AS · PL 253
6403/10-1 is a wildcat exploration wellbore in the Norwegian Sea, drilled by Norsk Hydro Produksjon AS, entered Oct 24, 2002, to 3,400 m in the Kvitnos Fm.
- 3,400
- m total depth · 3,397 m vertical
- 1,717
- m water depth
- Oct 24, 2002
- entered · completed Dec 30, 2002
- Kvitnos Fm
- at total depth · Late Cretaceous
- —
- m of core
- 80
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED DEC 30, 2004
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- SCARABEO 5 · Semisub steel
- Drilling days
- 68
- Kelly bushing elevation
- 25 m
- Maximum inclination
- 6.30000019°
- Drilling permit
- 1041-L
- Licensing round
- 16
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 64.06089° N, 3.00302° E
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
The exploration well 6403/10-1 was drilled to test the hydrocarbon potential in one of the segments of the PL 253 Solsikke dome structure. The Solsikke structure is situated in the north-western part of the outer Møre Basin, close to the Møre Marginal High, in the Norwegian Sea. The structure is defined as a large Tertiary dome comprising a thickness anomaly of Upper Cretaceous sediments. The primary target was the Nise and Intra Springar sandstones and the secondary target was the Intra Kvitnos sandstones. The well was drilled in a relatively low structural position on the southern part of the dome. The location was chosen to test the hydrocarbon potential above a clear flat event within the Nise Formation and at the same time penetrate the Springar in a position of anticipated good Springar reservoir quality near observed flat events within the Springar. The well should also test the intra Kvitnos Formation, but avoid faults within the formations and shallow gas observations. In addition, the spud location had to take into account the rough sea bottom.
Operations and results
Exploration well 6403/10-1 was spudded with the semi-submersible installation Scarabeo 5 on 24 October 2002 and drilled to TD at 3398 m in the Kvitnos Formation. No serious problems were encountered during drilling. The well was drilled with spud mud down to 2217 m and with a water-based glycol system (GLYDRIL) from 2217 m to TD.
Mudstone and siltstone were encountered in the Cretaceous reservoir section, with high content of siltstone in Nise. Sidewall cores of the siltstone in the Nise Formation showed high porosity but low permeability with no reservoir quality. The well did not prove any hydrocarbons. Organic geochemical analyses indicated immature formations throughout the well based on Rock-Eval Tmax and vitrinite reflectance readings. No significant amounts of C15+ hydrocarbons were detected in these analyses, confirming the on-rig shows analy
Around this wellbore
This wellbore on Sodir FactPages → · Press release →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.