NORWAY · WELLBORES · NPDID 4602

6403/10-1

Exploration · Wildcat · P&A · Dry · Norsk Hydro Produksjon AS · PL 253

5 documents: reports, logs, and plots →

6403/10-1 is a wildcat exploration wellbore in the Norwegian Sea, drilled by Norsk Hydro Produksjon AS, entered Oct 24, 2002, to 3,400 m in the Kvitnos Fm.

On the map →

3,400
m total depth · 3,397 m vertical
1,717
m water depth
Oct 24, 2002
entered · completed Dec 30, 2002
Kvitnos Fm
at total depth · Late Cretaceous
—
m of core
80
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED DEC 30, 2004

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
SCARABEO 5 · Semisub steel
Drilling days
68
Kelly bushing elevation
25 m
Maximum inclination
6.30000019°
Drilling permit
1041-L
Licensing round
16
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
64.06089° N, 3.00302° E

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

The exploration well 6403/10-1 was drilled to test the hydrocarbon potential in one of the segments of the PL 253 Solsikke dome structure. The Solsikke structure is situated in the north-western part of the outer Møre Basin, close to the Møre Marginal High, in the Norwegian Sea. The structure is defined as a large Tertiary dome comprising a thickness anomaly of Upper Cretaceous sediments. The primary target was the Nise and Intra Springar sandstones and the secondary target was the Intra Kvitnos sandstones. The well was drilled in a relatively low structural position on the southern part of the dome. The location was chosen to test the hydrocarbon potential above a clear flat event within the Nise Formation and at the same time penetrate the Springar in a position of anticipated good Springar reservoir quality near observed flat events within the Springar. The well should also test the intra Kvitnos Formation, but avoid faults within the formations and shallow gas observations. In addition, the spud location had to take into account the rough sea bottom.

Operations and results

Exploration well 6403/10-1 was spudded with the semi-submersible installation Scarabeo 5 on 24 October 2002 and drilled to TD at 3398 m in the Kvitnos Formation. No serious problems were encountered during drilling. The well was drilled with spud mud down to 2217 m and with a water-based glycol system (GLYDRIL) from 2217 m to TD.

Mudstone and siltstone were encountered in the Cretaceous reservoir section, with high content of siltstone in Nise. Sidewall cores of the siltstone in the Nise Formation showed high porosity but low permeability with no reservoir quality. The well did not prove any hydrocarbons. Organic geochemical analyses indicated immature formations throughout the well based on Rock-Eval Tmax and vitrinite reflectance readings. No significant amounts of C15+ hydrocarbons were detected in these analyses, confirming the on-rig shows analy

Around this wellbore

This wellbore on Sodir FactPages → · Press release →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.