NORWAY · WELLBORES · NPDID 509

30/3-1 R

Exploration · Appraisal · P&A · Shows · Den norske stats oljeselskap a.s · Huldra · PL 052

6 documents: reports, logs, and plots →

30/3-1 R is an appraisal exploration wellbore in the North Sea, drilled by Den norske stats oljeselskap a.s, entered Feb 1, 1982, to 4,421 m in the Statfjord Gp.

Discovery 30/2-1 Huldra · On the map →

4,421
m total depth · 4,421 m vertical
138
m water depth
Feb 1, 1982
entered · completed Apr 26, 1982
Statfjord Gp
at total depth · Late Triassic
16.4
m of core in 1 core
143
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED APR 26, 1984

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
DYVI DELTA · Semisub steel
Drilling days
85
Kelly bushing elevation
27 m
Maximum inclination
0°
Drilling permit
215-L2
Licensing round
4
Plugged and abandoned
Apr 26, 1982
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
60.90426° N, 2.66992° E

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Well 30/3-1 R is located just north of the Huldra Discovery. The primary well bore 30/3-1 was drilled in 1979 to a total depth of 3718 m where it was suspended due to an unexpected pressure build-up in the Early Cretaceous. The purpose of well 30/3-1 R was to re-enter the previously abandoned well and continue drilling beneath the 9 5/8" casing shoe to test sandstones in the Brent Group. Secondary objectives were sandstones in the Early Jurassic, Cook and Statfjord formations. Well 30/3-1 R (Phase 2) was planned to be drilled 50 m into the Triassic to a total prognosed depth of 4825 m.

Operations and results

Wildcat well 30/3-1 R was re-entered by the semi-submersible installation Dyvi Delta on 1 January 1982 and drilled to TD at 4421 m (4395 m TVD) in Late Triassic sediments in the Statfjord Formation. After the 9 5/8" casing had been drilled and cleaned out for cement plugs the string was lost in the hole when running in with a new bit. After several attempts to retrieve the fish, the hole was plugged back. A window was cut in the 9 5/8" casing from 3657 m to 3672 m and the hole was kicked off from this depth after problems with lost circulation had been solved. While drilling of the last part of the 8 1/2" hole several incidents of stuck pipe was experienced. This section was plugged back with cement. When displacing the second cement plug, the pipe got stuck. After cutting the 5" drill pipe an influx (gas and water) from the top of the Statfjord Formation was taken. The well built a deviation with maximum of 20.5° at 4165 m. The well was drilled with a Spersene XP 20/Magcogel/nut plug mud system from kick-off to TD.

Hydrocarbons were encountered in thin sandstones interbedded with limestone, coals and claystones over the interval from 3762 m to 3861 m in the Ness, Etive, and Rannoch formations in the Brent group. One core was cut from 3863.6 m to 3875.2 m in the Brent Group. No fluid sample w

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.