NORWAY · WELLBORES · NPDID 6030
15/6-10
Exploration · Wildcat · P&A · Gas/condensate · ExxonMobil Exploration and Production Norway AS · PL 029 B
15/6-10 is a wildcat exploration wellbore in the North Sea, drilled by ExxonMobil Exploration and Production Norway AS, entered Feb 7, 2009, to 3,700 m in the Skagerrak Fm.
Discovery 15/6-10 (Freke) · On the map →
- 3,700
- m total depth · 3,693 m vertical
- 111.3
- m water depth
- Feb 7, 2009
- entered · completed Apr 6, 2009
- Skagerrak Fm
- at total depth · Late Triassic
- —
- m of core
- 119
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED APR 6, 2011
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- BREDFORD DOLPHIN · Semisub steel
- Drilling days
- 59
- Kelly bushing elevation
- 25 m
- Maximum inclination
- 8°
- Drilling permit
- 1224-L
- Licensing round
- 2-A
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 58.68215° N, 1.83757° E
- Hydrocarbons in
- Sleipner Fm · Middle Jurassic
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Well 15/6-10 was drilled on the Gudrun Terrace in the South Viking Graben of the North Sea. The main objectives of the well were to test the hydrocarbon and reservoir potential in the Hugin and Sleipner sandstones of the Freke prospect. The main target was the Hugin Formation, prognosed at 3495 m TVD RKB, and the secondary target was the Sleipner Formation.
Operations and results
Wildcat well 15/6-10 was spudded with the semi-submersible installation Bredford Dolphin on 7 February 2009 and drilled to TD at 3700 m in the Late Triassic Skagerrak Formation. The well experienced some deviation difficulties in the 17 1/2" and 12 1/4" sections. The 17 1/2" section started out well but with fairly high torque and stick-slip levels. When entering the Skade Fm the assembly started to build angle. Despite attempts to reduce the building tendency, the angle kept building 0.5- 0.7 degrees per stand drilled. When drilling at 1838 m, the 17 1/2" assembly twisted off in an extension sub just below the bottom stabilizer, approximately 18 m above the bit. The fish was retrieved at first attempt. The 17 1/2" were finished on a motor run to correct the well path. In 12 1/4" section, steering commenced in order to correct the well path back towards the target centre. Initially steering proved to be relatively easy but turned impossible once entering chalk due to very poor toolface control. The well was drilled with spud mud down to 696 m, with KCl/GEM water based mud from 696 m to 2109 m, and with Performadril water based mud from 2109 m to TD.
The well penetrated several Tertiary sands (Utsira, Skade, and Heimdal Formations), all water-filled. The primary target Hugin Formation was not encountered although an equiv
Around this wellbore
This wellbore on Sodir FactPages → · Press release →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.