NORWAY · WELLBORES · NPDID 7180

2/1-16 S

Exploration · Wildcat · P&A · Dry · Talisman Energy Norge AS · PL 299

1 document: reports, logs, and plots →

2/1-16 S is a wildcat exploration wellbore in the North Sea, drilled by Talisman Energy Norge AS, entered May 10, 2013, to 3,891 m in the Ula Fm.

On the map →

3,891
m total depth · 3,770 m vertical
67
m water depth
May 10, 2013
entered · completed Jul 13, 2013
Ula Fm
at total depth · Late Jurassic
—
m of core
—
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED JUL 13, 2015

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
MÆRSK GIANT · Jack-up 3 legs
Drilling days
64
Kelly bushing elevation
44 m
Maximum inclination
34.79999924°
Drilling permit
1445-L
Licensing round
TFO2003
Plugged and abandoned
Jul 13, 2013
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
56.85048° N, 3.31464° E

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Well 2/1-16 S was drilled on the Frode prospect on the Sørvestlandet High south-west of the Gyda Field in the North Sea. The primary objective was to prove hydrocarbons in the Late Jurassic Ula Formation sandstones.

Operations and results

Wildcat well 2/1-16 S was spudded with the jack-up installation Mærsk Giant on 13 July 2013 and drilled to TD at 3891 m (3770 m TVD) in the Late Jurassic Ula Formation. A 12-1/4" pilot hole was drilled with weighted WBM to approximately 844 m RKB. No shallow gas present. The well was drilled vertical down to 2420 m and deviated from there to TD. The well was drilled with seawater down to 144 m, with water based KCl mud from 144 m to 861 m, and with Innovert oil based mud from 861 m to TD.

A thick Ula reservoir sandstone with very good reservoir properties was penetrated at 3490 m, 22 m TVD deeper than prognosed. The reservoir was water wet with all pressure points through the Ula Formation on the same water gradient. No oil shows above the oil-based mud were recorded in the well.

No cores were cut. No fluid samples were taken.

The well was permanently abandoned on 13 July 2013 as a dry well.

Testing

No drill stem test was performed.

Around this wellbore

This wellbore on Sodir FactPages → · Press release →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.

Developers: this page as JSON is GET /v1/data/norway/wells/7180, documented in the API reference.