30/2-1
Exploration · Wildcat · P&A · Gas/condensate · Den norske stats oljeselskap a.s · Huldra · PL 051
30/2-1 is a wildcat exploration wellbore in the North Sea, drilled by Den norske stats oljeselskap a.s, entered May 17, 1982, to 4,243 m in the Statfjord Gp.
Discovery 30/2-1 Huldra · On the map →
- 4,243
- m total depth · 4,237 m vertical
- 125
- m water depth
- May 17, 1982
- entered · completed Oct 12, 1982
- Statfjord Gp
- at total depth · Early Jurassic
- 108.8
- m of core in 11 cores
- 164
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED OCT 12, 1984
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- DYVI DELTA · Semisub steel
- Drilling days
- 149
- Kelly bushing elevation
- 30 m
- Maximum inclination
- 7.75°
- Drilling permit
- 328-L
- Licensing round
- 4
- Plugged and abandoned
- Mar 15, 2019
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 60.86817° N, 2.64699° E
- Hydrocarbons in
- Brent Gp · Middle Jurassic
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Well 30/2-1 is located roughly mid-way between the Oseberg Field complex and the Kvitebjørn Field in the Northern North Sea. The primary objective of the well was sandstones of Middle Jurassic age. Secondary objectives were sandstones of Paleocene and Late/Early Triassic age.
Operations and results
Wildcat well 30/2-1 was spudded with the semi-submersible installation Dyvi Delta on 17 May 1982 and drilled to TD at 4243 m, 133 m into the Early Jurassic Statfjord Formation. A total of 125 days were spent on the drilling phase, which was 5 days more than prognosed. Twelve days were lost due to problems with lost circulation, gas influx, stuck pipe and a leaking liner overlap in the 8 1/2" hole section. Three and a half days were lost to free the 13 3/8" casing when this got stuck at 1998 m. Most of those days were caught up because total depth was reached 357 m shallower than prognosed, and because of successfully turbodrilling with diamond bits in the 12 1/4" and 6" hole section. The well was drilled with spud mud down to 1035 m, with Gypsum mud from 1035 m to 1860 m, and with Gypsum/Lignosulphonate mud from 1860 m to 2155 m. An oilfaze/pipelax and an Imco spot/pipelax pill was spotted at 1998 m to free the pipe. From 2155 to TD the well was drilled with Spersene XP 20 (Lignosulphonate).
Hydrocarbons were encountered in the Brent group. The secondary prospects were found to be water wet, although oil shows were recorded in dolomite between 1852 m and 1911 m in the Eocene and in a 30 cm thick sandstone bed at 1952 m in the Late Paleocene Balder Formation. Weak shows were also recorded on sandstones from 4119 m to 4202 m in the Statfjord Formation.
Eleven cores were cut with a total recovery of 108.8 metres. Two cores were cut from 1952 m to 1969.5 m in the Late Paleocene Balder Formation, while 9 cores were cut from 3696 m to 3794 m in the Ness, Etive, and Rannoch Formations of the Brent Group. Fi
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/72, documented in the API reference.