NORWAY · WELLBORES · NPDID 8288
35/9-13
Exploration · Wildcat · Junked · Not applicable · Spirit Energy Norge AS · PL 682
35/9-13 is a wildcat exploration wellbore in the North Sea, drilled by Spirit Energy Norge AS, entered Dec 25, 2017, to 3,223 m in the Rødby Fm.
- 3,223
- m total depth · 3,223 m vertical
- 365
- m water depth
- Dec 25, 2017
- entered · completed Jan 20, 2018
- Rødby Fm
- at total depth · Early Cretaceous
- —
- m of core
- —
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED SEP 3, 2019
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- SONGA ENABLER · Semisub steel
- Drilling days
- 27
- Kelly bushing elevation
- 32 m
- Maximum inclination
- 1°
- Drilling permit
- 1674-L
- Licensing round
- TFO2012
- Plugged and abandoned
- Mar 29, 2018
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 61.42232° N, 3.82771° E
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Well 35/9-13 was drilled to test the Tethys prospect on the Måløy slope in the northern North Sea. The primary objective was to test the hydrocarbon potential in Intra-Heather sandstone of Oxfordian age. Dependent on the results of the well, optional production testing was planned to test reservoir productivity, in addition to an optional side-track to further evaluate the prospect.
Operations and results
A 9 7/8" pilot hole was drilled 30 m off location from the 35/9-13 well. No shallow gas or water flow was observed.
Wildcat well 35/9-13 was spudded with the semi-submersible installation Songa Enabler on 25 December. At 2555 m in the Tryggvason Formation the bit drilled into a fault zone and total losses occurred. Losses were cured with fibrous materials and reduction of mud weight. Drilling of the 12 ¼ hole commenced to 3223 m in the Early Jurassic Rødby Formation. While running in hole with the 8 1/2" BHA the operation was stopped at 1770 m due to observation of a
water flow around the well head. The water flow was identified flowing outside the 20” casing because of bad cement bond. The water most likely came from ca 661 m in the top of a Paleogene sand. It was decided to P&A the well for safety reasons. The well was drilled with seawater and hi-vis pills down to 948 m, with KCl/GEM/polymer mud from 948 m to 1822 m, and with Innovert oil-based mud from 1822 m to TD.
The well did not fulfil its objectives.
The only log on wire line was a CBL log to evaluate the cement behind the casing and source of the shallow water flow. No reliable formation temperature co
Around this wellbore
This wellbore on Sodir FactPages → · Press release →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/8288, documented in the API reference.