NORWAY · WELLBORES · NPDID 862

6/3-2

Exploration · Wildcat · P&A · Shows · Den norske stats oljeselskap a.s · PL 086

6 documents: reports, logs, and plots →

6/3-2 is a wildcat exploration wellbore in the North Sea, drilled by Den norske stats oljeselskap a.s, entered Nov 21, 1985, to 4,091 m in the Rotliegend Gp.

On the map →

4,091
m total depth · 4,085 m vertical
89
m water depth
Nov 21, 1985
entered · completed Mar 10, 1986
Rotliegend Gp
at total depth · Early Permian
218.6
m of core in 11 cores
154
°C bottom-hole temperature

SODIR FACTPAGES · RECORD UPDATED MAR 1, 2026 · RELEASED MAR 10, 1988

On file for this wellbore

What the Directorate holds from this wellbore. Each opens the section that lists it.

Drilling

Drilling facility
ROSS ISLE · Semisub steel
Drilling days
110
Kelly bushing elevation
22 m
Maximum inclination
9.19999981°
Drilling permit
492-L
Licensing round
8
Plugged and abandoned
—
Core samples available
Yes
Cuttings samples available
Yes
Position · ED50
57.90722° N, 1.98727° E

Well history

WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE

General

Well 6/3-2 was drilled on the gamma structure on an early Permian formed fault block, 1.4 km from the Norwegian/UK median line. The primary objective was to test Jurassic/Triassic sandstones at different levels for possible hydrocarbon accumulations. Secondary objectives were to test Cretaceous porous/fractured limestone/chalk and Rotliegend sandstone. The prognosed TD was 4325 m. The location was chosen due to the proximity to mature source rocks and oil/gas discoveries in British waters. Seismic anomalies indicated shallow gas. Due to this the original planned well location was abandoned and a new location was chosen 500 m to the east.

Operations and results

Wildcat well 6/3-2 was spudded with the semi-submersible installation ROSS Isle 21 November 1985 and drilled to TD at 4091 m in the Early Permian Rotliegend Formation. Some hole problems were experienced in the top of the 12 1/4" hole section. 9 5/8" casing was set close to the Zechstein formation before drilling the 8 1/2" hole into the salt. At 3772 m, an over-pressured zone of dolomite/slate was encountered. It was anticipated that one had found a "floating lens" enclosed in the evaporites. The well started flowing and pressure was increased to 2.05 g/cc in order to stabilise the well. Because of this a 7" liner had to be set in the middle of the salt. A 6" hole was drilled to base of the Zechstein Formation and a 5" liner was set in order to be able to reduce mud weight through the Rotliegend sandstone. The well was drilled with seawater/hi-vis pills/pre-hydrated bentonite through the top sections to 622 m, with gypsum/polymer mud from 622 m to top of the salt at 3400 m, and with Safemul oil based mud from 3400 m to TD. No indication of shallow gas was encountered at this location.

Top Cretaceous came in at 2511 m. There were some shows in the Cretaceous limestone/chalk. However, logs, cores and cuttings showed that the re

Around this wellbore

This wellbore on Sodir FactPages →

About this data

Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.

Developers: this page as JSON is GET /v1/data/norway/wells/862, documented in the API reference.