NORWAY · WELLBORES · NPDID 316
15/5-2
Exploration · Wildcat · Suspended · Gas · Norsk Hydro Produksjon AS · Eirin · PL 048
15/5-2 is a wildcat exploration wellbore in the North Sea, drilled by Norsk Hydro Produksjon AS, entered Aug 16, 1978, to 4,322 m in the Hegre Gp.
Discovery 15/5-2 Eirin · On the map →
- 4,322
- m total depth
- 121
- m water depth
- Aug 16, 1978
- entered · completed Dec 16, 1978
- Hegre Gp
- at total depth · Triassic
- 15
- m of core in 2 cores
- 127
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED NOV 4, 2026 · RELEASED DEC 16, 1980
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- TREASURE SEEKER · Semisub steel
- Drilling days
- 123
- Kelly bushing elevation
- 25 m
- Maximum inclination
- 5.75°
- Drilling permit
- 200-L
- Licensing round
- 3
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 58.64354° N, 1.60458° E
- Hydrocarbons in
- Vestland Gp · Middle Jurassic
- Hydrocarbons in
- Hegre Gp · Triassic
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
General
Well 15/5-2 was drilled in the Ve Sub-basin in the North Sea, north of the Sleipner Vest Field and 15/5-1 Gina Krog Discovery. The main objective of the well was to test possible hydrocarbon accumulations in Middle to Late Jurassic Bathonian/Callovian transgressive sandstones and Middle Jurassic Bajocian deltaic sandstones. The well was located in a purposely off-crestal position on an approximately 16 km2 large structure some 7 km north-west of the 15/5-1 discovery.
The well was planned to penetrate into the Triassic with a projected total depth of 4500 m.
Operations and results
Wildcat well 15/5-2 was spudded with the semi-submersible installation Treasure Seeker on 16 August 1978 and drilled to TD at 4322 m in the Triassic Hegre Group. At 1267 m, the string unscrewed in a tight section, but it was fished without problems. After drilling to 2293 m, the string stuck when pulling out of hole. This time the fish was not recovered and a sidetrack was performed with kick-of at 1775 m. Heavy weather caused further delays, otherwise the drilling went forth without significant problems to TD. The well was drilled with seawater mud mixed with gel and Spersene down to 454 m, and with a Spersene/XP-20 (lignosulphonate) mud from 454 m to TD. At 2232 m 1% Diesel was added to the mud.
Two hydrocarbon bearing sandstone intervals were penetrated by the well. In the Jurassic, only a thin Early to Middle Bathonian sandstone development was penetrated between 4035 m and 4055 m. Interbeds of siltstones and shales reduced the 20 m gross pay to a net pay of 7.3 m from wireline log interpretation. Average porosity and average water saturation over the pay interval was calculated to 14.3 and 41
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/316, documented in the API reference.