25/12-1 is a wildcat exploration wellbore in the North Sea, drilled by A/S Norske Shell, entered Oct 3, 1973, to 2,865 m in the No Group Defined.
- 2,865
- m total depth
- 135
- m water depth
- Oct 3, 1973
- entered · completed Dec 23, 1973
- No Group Defined
- at total depth · Devonian
- 5.6
- ft of core in 1 core
- 93
- °C bottom-hole temperature
SODIR FACTPAGES · RECORD UPDATED FEB 20, 2026 · RELEASED DEC 23, 1975
On file for this wellbore
What the Directorate holds from this wellbore. Each opens the section that lists it.
Drilling
- Drilling facility
- SEDCO 135 G · Semisub steel
- Drilling days
- 82
- Kelly bushing elevation
- 34 m
- Maximum inclination
- 2.5°
- Drilling permit
- 95-L
- Licensing round
- 1-A
- Plugged and abandoned
- —
- Core samples available
- Yes
- Cuttings samples available
- Yes
- Position · ED50
- 59.02972° N, 2.82142° E
Well history
WRITTEN BY THE NORWEGIAN OFFSHORE DIRECTORATE
Well 25/12-1 is located on the Patch Bank Ridge between the Utsira High and the Stord Basin in the North Sea. The well was designed to test Paleocene sand and late Cretaceous chalk prospects (found oil bearing in the adjacent Esso blocks). Additional objectives were the Mesozoic and possibly older sands, which formed part of a monocline, east dipping subcrop below this structure. The well was programmed to investigate the entire sedimentary sequence down to igneous/metamorphic basement, interpreted to occur at approximately 2743 m.
Operations and results
Wildcat well 25/12-1 was spudded with the semi-submersible installation SEDCO 135 G on 3 October 1973 and drilled to TD at 2865 m in rocks of possible Devonian age. The spud was delayed due to rig repairs in Hamburg. This resulted in the well being drilled during the worst of the winter weather. Due to adverse weather and bad anchoring conditions, 14.5 days were spent anchoring the rig. A total of 19.7 days was lost directly due to weather during drilling and abandoning. A further 8.7 days were lost repairing underwater equipment, much of which was also due to weather damage. The well was drilled with seawater and bentonite down to 463 m and with a seawater / lignosulphonate mud from 463 m to TD.
The Oligocene-Eocene sands of the Hordaland Group were water bearing and the Paleocene sands absent. The Chalk section (Tor and Hod formations) showed poor reservoir characteristics and was also water bearing. Below the Late Jurassic shale sequence sands and conglomerates of Middle Jurassic age and older were penetrated. The sands were penetrated in a down dip position on a monoclinal structure rising towards block 25/11. Middle Jurassic (Vestland Group) sands were encountered at 2244 m with porosity up to 30 %, averaging 18 %. Conglomerates were encountered at 2425 m and extended down to 2671 m. From this point down to TD at 2865 m the well drilled a thick water bearing sand sequence. This possible Devonia
Around this wellbore
This wellbore on Sodir FactPages →
About this data
Norwegian Offshore Directorate (Sodir) FactPages, mirrored nightly and used under the Norwegian Licence for Open Government Data (NLOD). Depths are metres along the wellbore from the kelly bushing unless a row gives its own unit; older cores are filed in feet. A zero the Directorate files for an unmeasured pressure, density, or temperature is shown as a dash.
Developers: this page as JSON is GET /v1/data/norway/wells/374, documented in the API reference.